What 60 days of payment delay cost you: the calculation

A customer who pays at 60 days is cash you lend them. The method to put a number on each day of delay, from the end of the job to the money landing in your account.

Jérôme Knops

By Jérôme Knops

Published November 28, 2026 · 4 min read

Ask an AI

The question comes pre-written, with this article's address.

A joiner finishes an installation, invoices three weeks later, and the customer pays at 30 days, then a little after. Between the last screw and the transfer, two months have gone by. For those two months, the company paid wages, timber and hardware out of its own pocket. This credit extended to the customer appears on no cost line, yet it is paid for: in overdraft, in credit lines, or in projects nobody dares to start.

One payment delay, three hidden delays

When people say "60 days", they are blending three separate durations, which have neither the same cause nor the same fix:

  • The delay before invoicing: the time between the end of the job and the invoice going out. It depends only on you.
  • The agreed delay: the 30 days (or more) written on the quote or the invoice.
  • The lateness: the days added because the invoice went to the wrong place, contained a mistake, or nobody chased it.

The first and the third are fixed inside your company. The second is negotiated at signing. Adding them into a single figure hides the one you control.

The method in three steps

1. Measure your real delay, invoice by invoice

Take the last 30 invoices that were paid. For each, note the date the work ended, the date the invoice was sent and the date the money arrived. Average each gap. The result almost always surprises: the real delay runs ten to twenty days longer than the one people believed they had.

2. Work out what one day of delay is worth

One more day of delay is one day of revenue left outside, at your expense. You turn it into a cost with the rate at which you finance your cash (overdraft, credit line, or what that capital would earn elsewhere).

The formula: annual revenue ÷ 365 × financing rate = yearly cost of one day of delay.

3. Multiply by your days

The yearly cost of the total delay is the cost of one day multiplied by the number of days. More usefully, so is each delay taken separately: that is how you see which one deserves attacking first.

A worked example

Take a joinery firm of about ten people. Assumptions: €960,000 of revenue invoiced a year, a financing rate of 6% a year, and a measured average delay of 60 days.

DelayDaysCalculationYearly cost
Before invoicing2020 × €158€3,160
Agreed with the customer3030 × €158€4,740
Lateness1010 × €158€1,580
Total60€9,480

One day of delay costs about €158 a year here (960,000 ÷ 365 × 6%). Taken alone, the figure is not spectacular. What matters is the top line: 20 days before the invoice even leaves, more than €3,000 a year for a task that depends on nobody but you. Halving that delay earns as much as renegotiating a third of the payment terms.

On top of that comes what the calculation does not show: about €160,000 of invoices waiting is that much you cannot commit to stock, a machine or a hire.

What changes with an application built for your company

The delay before invoicing is the one an application shortens most easily, because it almost always comes from information that did not travel. When the team lead closes the job from their phone, the invoice is prepared from the signed quote and the hours actually spent, with no one in the office having to piece it together. Lateness shrinks the same way: an invoice sent with the right amount and the right recipient triggers its own reminder on the due date, without anyone having to remember on a Friday.

You also see, on one screen, the three delays of each file: how many days before invoicing, how many days agreed, how many days late. No more redoing the calculation by hand every quarter.

What not to do

Do not try to shorten everything at once by tightening payment terms for every customer. A loyal customer who always pays, at 45 days, is worth more than one who pays at 30 days and who you lose. The first gain almost always sits in your own delay before invoicing, which risks annoying no one.

Payment delay: the key takeaways

A payment delay can be priced: annual revenue divided by 365, multiplied by the rate at which you finance your cash, gives the cost of one day, which you then multiply by its days. It breaks down into three durations, and the first (the time before invoicing) is the one you control entirely.

For what comes next, see how to read customer outstanding by age and why you should invoice the day the work is finished. The construction sector page covers the specific cases.