The 5% retention money: who owes it, and when to release it
A private construction contract withholds 5% on every payment. What French law says about releasing it after one year, and what can block it.

By Jérôme Knops
Published November 20, 2026 · 4 min read

A private construction contract almost always carries the same clause: 5% withheld on every payment, until the snagging list is cleared. One year after handover, that money must go back to the contractor, by right. In between, a 1971 French law sets out precise rules that many general contractors only discover when they claim what they are owed, too late to act.
What gets withheld, and what must happen to it
On private construction contracts, French law n° 71-584 of 16 July 1971 caps retention money at 5% of the contract amount. It covers one thing only: making good on the snagging items noted at handover. It is not the same as the one-year statutory defects warranty, nor a performance bond.
One point many owners miss: the withheld amount cannot sit in their own bank account. Only two routes are allowed:
- Escrow with a third party accepted by both sides, in practice the Caisse des dépôts et consignations.
- A personal, joint and several bank guarantee, which the contractor can offer instead of the retention, to collect the full price upfront.
Keeping the money in the owner's own account, with no escrow and no guarantee, does not comply with the law. That irregularity can trigger penalties, and gives the contractor solid grounds to challenge the retention.
The one-year countdown
The retention, or the guarantee that replaces it, is released by right one year after the handover date, whether that handover came with snagging items or without. Once that year passes, the money goes back to the contractor with no further step on their part.
The owner keeps only one way out: a reasoned objection, sent before the one-year deadline, by registered letter. Three conditions, all required:
- The deadline. A letter posted the day after the anniversary arrives too late, even by a few hours.
- The reason. Specific defects, identified snagging items, a matching amount. A general objection does not hold.
- The recipient. The escrow holder or the bank that issued the guarantee, never the contractor alone.
An objection missing any one of these three points is irregular, and the full retention stays due.
Tracking retention money across overlapping projects
The risk is not losing a retention: it is forgetting it exists, because it falls due twelve months after a project everyone already considers closed. Take a worked example, as an assumption. A general contractor runs six projects at once, each worth €180,000 excluding VAT on average.
| Item | Amount |
|---|---|
| Average contract value | €180,000 excl. VAT |
| Retention money (5%) | €9,000 |
| Projects running at once | 6 |
| Total tied up over the year | €54,000 |
Each retention has its own handover date, so its own one-year deadline. Across six overlapping projects, that means six different dates to watch, each with its own file of open or cleared snagging items. One line per project is enough: handover date, method used (escrow or guarantee), snagging items open or cleared, deadline for an objection.
What not to do
Vague snagging notes at handover weaken everything that follows: a handover report that says "finishes to review" without naming the actual defects will not, a year later, support a reasoned objection. Handover is where the clarity of everything that follows gets decided, not a formality to rush through.
What changes with an application built for the business
Retention money is not a one-size-fits-all module: its rate, its method (escrow or guarantee) and how snagging items get handled change from one company to another, sometimes from one contract to the next. In an application built for the business, these rules are taken as they are actually practiced, not forced into a fixed model.
Once the rules are set, this becomes possible: every project carries its handover date, and the one-year deadline follows from it automatically. An alert goes out as the deadline nears, addressed to the person who would need to prepare a reasoned objection, before it is too late to send one. Snagging items stay attached to the handover report signed on site, dated, with their status, instead of scattered across emails someone has to dig up a year later.
Retention money: the key takeaways
Retention money, capped at 5%, has followed the same rules since 1971: it must be held in escrow or replaced by a guarantee, never kept in the owner's own account, and it is released by right one year after handover, unless a reasoned objection is sent in time. Across several overlapping projects, it is that date, specific to each contract, that most often slips past.
The right habit is not to renegotiate the clause, but to know, at any moment, how much is tied up and when each amount is due back, so you act before the deadline rather than finding out during a dispute six months too late.